UNDERGROUND CAR PARK NEARING COMPLETION
If you were to peer into the hole at the front of the Club, you’ll be surprised to see how close to the top construction has progressed to complete the multi storey underground car park.
Parkview are currently working on forming the two new areas of basement level 1 – one side is the car park, the other side is the Club’s new loading dock. The new loading dock will have enough room to receive four trucks at any one time and will have ample space for the vehicles to reverse in so that they can load and unload stock efficiently. From that point, stock can be quickly dispersed to different sections of the Club through a series of underground tunnels that link one end of Canterbury to the other.
The entire space and the surrounding areas that used to be Galaxy Play Area have also been demolished as part of the planned new bistro al fresco extension. The next step is to join the Club’s existing foundation slab to the new West wing build.